Hoang Hai wind farm

0 27

Hoang Hai wind farm will have 16 turbines, and the foundations have been completed for more than 20 of them. Five turbines are being installed, and the investors hope the farm will become operational by the end of October.

Then it will be eligible for the incentive feed-in tariff of 9.8 U.S. cents per kilowatt-hour for offshore projects and 8.5 cents for onshore.

The project was completed on schedule with absolute safety.

The project information is as follows:
Investor: Hoang Hai Wind Power JSC.
Turbine OEM: Envision, model EN141-3.3MW.
Number of turbines: 16 turbines
Project location: Huong Hoa district, Quang Tri province.
Scope of work: Crane & installation and commissioning (From August 2021 to October 2021)

You might also like
Leave A Reply

Your email address will not be published.


The reCAPTCHA verification period has expired. Please reload the page.