Hoang Hai wind farm
Hoang Hai wind farm will have 16 turbines, and the foundations have been completed for more than 20 of them. Five turbines are being installed, and the investors hope the farm will become operational by the end of October.
Then it will be eligible for the incentive feed-in tariff of 9.8 U.S. cents per kilowatt-hour for offshore projects and 8.5 cents for onshore.
The project was completed on schedule with absolute safety.
The project information is as follows:
Investor: Hoang Hai Wind Power JSC.
Turbine OEM: Envision, model EN141-3.3MW.
Number of turbines: 16 turbines
Project location: Huong Hoa district, Quang Tri province.
Scope of work: Crane & installation and commissioning (From August 2021 to October 2021)